• Contact Us
  • About Us
  • Advertise
  • Donate
  • Login
Watchdog Uganda
  • Home
  • News
    • National
    • Politics
    • World News
    • Media Outreach Newswire
    • Africa News
    • Tourism
    • Community News
    • Luganda
    • Sports
      • Football
      • Motorsport
  • Op-Ed
    • #Out2Lunch
    • Conversations with
    • Politics
    • Relationships
  • Business
    • Agriculture
    • CEOs & Entrepreneurs,
    • Companies
    • Finance
    • Products
    • RealEstate
    • Technology
  • Entertainment
    • Lifestyle
  • People
    • Showbiz
      • Salon Mag
  • Special Report
    • Education
    • Voices
  • Reviews
    • Products
    • Events
    • Hotels
    • Restaurants
    • Places
  • WD-TV
  • Donate
  • China News
No Result
View All Result
  • Home
  • News
    • National
    • Politics
    • World News
    • Media Outreach Newswire
    • Africa News
    • Tourism
    • Community News
    • Luganda
    • Sports
      • Football
      • Motorsport
  • Op-Ed
    • #Out2Lunch
    • Conversations with
    • Politics
    • Relationships
  • Business
    • Agriculture
    • CEOs & Entrepreneurs,
    • Companies
    • Finance
    • Products
    • RealEstate
    • Technology
  • Entertainment
    • Lifestyle
  • People
    • Showbiz
      • Salon Mag
  • Special Report
    • Education
    • Voices
  • Reviews
    • Products
    • Events
    • Hotels
    • Restaurants
    • Places
  • WD-TV
  • Donate
  • China News
No Result
View All Result
Watchdog Uganda
No Result
View All Result

Busega-Mpigi Expressway project loan approved

Watchdog Uganda by Watchdog Uganda
3 hours ago
in News
0 0
ShareTweetSendShare

The Busega-Mpigi Expressway project works are expected to resume, following approval of a loan of Euros188.18 million (Shs781.04 billion) from the African Development Bank and Euros28.31 million (Shs117.46 billion) from the African Development Fund.

The loan, approved by Parliament during plenary sitting on Tuesday, 28 October 2025 is additional financing for the construction of the expanded 27-kilometre expressway.

The motion for the resolution of Parliament to approve the loan was moved by the Minister of State for Trade, Industry and Cooperatives (Industry), Hon. David Bahati.

Presenting the report of the Committee on National Economy, Deputy Chairperson, Hon. Robert Migadde, justified the additional financing, saying that government entered into an agreement with the contractor without adequate designs at an original cost of Shs547.5 billion which later increased to Shs1.35 trillion after the designs were submitted.

“In addition, the original project route alignment was re-aligned as the additional work items were considered integral to the functionality of the expressway as a toll road, resulting in an increased project scope of works,” said Migadde.

According to the committee’s report, additional financing was further required to cater for the increase of Project Affected Persons (PAPs) which was occasioned by the expansion of the project scope.

Migadde explained that the original PAPs were 2,885 but the re-alignment of the project route saw the number increase to 4,222 valued at over 167.7 billion.

“Out of the 4,222 approved Project Affected Persons, 2,585 have been paid valued at over Shs111.7 billion, leaving a total of 1,637 unpaid PAPs valued at over Shs5 billion,” said Migadde.

To mitigate further delays, the committee recommended that the works ministry should ensure that the contractor prioritises works in the unencumbered sections.

A minority report was, however, presented by Hon. Charles Tebandeke (Bbale County), also signed by Hon. Hassan Kirumira (NUP, Katikamu County South), wherein they urged lawmakers to stand-over the loan approval until the government chief valuer carries out a fresh valuation of compensation for all PAPs to ascertain the current costs.

Hon. Muhammad Muwanga Kivumbi (NUP, Butambala County) cautioned Parliament against approving the loan before ascertaining the exact funds required, saying that the project cost seemed exorbitant.

“What justification does government have to construct a kilometre at US$14 million. Parliament should move cautiously,” Muwanga Kivumbi said.

Kira Municipality Member of Parliament, Hon. Ibrahim Ssemujju, however, called for expeditious completion of the project, saying that the traffic on the Busega-Mpigi road is a nightmare.

“I am concerned that the Busega-Mpigi expressway has delayed and I will do anything to facilitate the completion of that road. I usually do not support loans but for this particular one, we need government to commit and the rest we shall investigate,” Ssemujju said.

 

 

Busega-Mpigi Expressway project loan approved
Breadcrumb
Home News Busega-Mpigi Expressway project loan approved

Minister Katumba Wamala (third, left), Hon. Charles Tebandeke (right, with back to camera) and other MPs in the Chamber on Tuesday, 28 October 2025
Posted On
Wednesday, 29th October 2025

The Busega-Mpigi Expressway project works are expected to resume, following approval of a loan of Euros188.18 million (Shs781.04 billion) from the African Development Bank and Euros28.31 million (Shs117.46 billion) from the African Development Fund.

The loan, approved by Parliament during plenary sitting on Tuesday, 28 October 2025 is additional financing for the construction of the expanded 27-kilometre expressway.

The motion for the resolution of Parliament to approve the loan was moved by the Minister of State for Trade, Industry and Cooperatives (Industry), Hon. David Bahati.

Presenting the report of the Committee on National Economy, Deputy Chairperson, Hon. Robert Migadde, justified the additional financing, saying that government entered into an agreement with the contractor without adequate designs at an original cost of Shs547.5 billion which later increased to Shs1.35 trillion after the designs were submitted.

“In addition, the original project route alignment was re-aligned as the additional work items were considered integral to the functionality of the expressway as a toll road, resulting in an increased project scope of works,” said Migadde.

According to the committee’s report, additional financing was further required to cater for the increase of Project Affected Persons (PAPs) which was occasioned by the expansion of the project scope.

Migadde explained that the original PAPs were 2,885 but the re-alignment of the project route saw the number increase to 4,222 valued at over 167.7 billion.

“Out of the 4,222 approved Project Affected Persons, 2,585 have been paid valued at over Shs111.7 billion, leaving a total of 1,637 unpaid PAPs valued at over Shs5 billion,” said Migadde.

To mitigate further delays, the committee recommended that the works ministry should ensure that the contractor prioritises works in the unencumbered sections.

A minority report was, however, presented by Hon. Charles Tebandeke (Bbale County), also signed by Hon. Hassan Kirumira (NUP, Katikamu County South), wherein they urged lawmakers to stand-over the loan approval until the government chief valuer carries out a fresh valuation of compensation for all PAPs to ascertain the current costs.

Hon. Muhammad Muwanga Kivumbi (NUP, Butambala County) cautioned Parliament against approving the loan before ascertaining the exact funds required, saying that the project cost seemed exorbitant.

“What justification does government have to construct a kilometre at US$14 million. Parliament should move cautiously,” Muwanga Kivumbi said.

Kira Municipality Member of Parliament, Hon. Ibrahim Ssemujju, however, called for expeditious completion of the project, saying that the traffic on the Busega-Mpigi road is a nightmare.

“I am concerned that the Busega-Mpigi expressway has delayed and I will do anything to facilitate the completion of that road. I usually do not support loans but for this particular one, we need government to commit and the rest we shall investigate,” Ssemujju said.

Hon. Bahati consulting with the Deputy Speaker, Thomas Tayebwa, during plenary
Deputy Speaker, Thomas Tayebwa, said that completion of the project is crucial and urged the Minister of Works and Transport to give reassurance that the road works will connect to the Kampala-Entebbe Expressway, Ndeeba, Mityana and the Northern bypass.

The minister, Gen. Edward Katumba Wamala, said that the new design includes auxiliary roads, connecting to Mityana and Kasangi.

“There will be a complex interchange around Kyengera which will connect the Entebbe expressway, Mityana and Northern bypass. All this will be treated by the interchange and it is part if the reason we require additional funding,” Katumba Wamala said.

He added that the expanded works include four toll gates and bridges which were not considered in the original design.

“I want to say that we commit to address all the issues raised in the minority report and main report and I want to assure Parliament that the funds spent will be recovered because it is a toll road,” he said.

The Busega-Mpigi Expressway is multinational with Rwanda, Burundi and the Democratic Republic of Congo, whose works started in 2020.


Do you have a story in your community or an opinion to share with us: Email us at editorial@watchdoguganda.com
ShareTweetSendShare

Related Posts

News

Forget Bobi Wine’s Kiwani Politics; Uganda’s New Political Darling is Born in Luzzi’s Unfiltered Truth

29th October 2025 at 23:50
ACP Rusoke Kituuma
News

Police Warn NUP Supporters Over Escalating Attacks on Officers Amid Campaign Tensions

29th October 2025 at 22:40
News

Youth Advocate Nyanzi Martin Luther Appeals for Financial Backing to Expand Apex Digital Skills Initiative

29th October 2025 at 22:37
Next Post

Forget Bobi Wine's Kiwani Politics; Uganda's New Political Darling is Born in Luzzi's Unfiltered Truth

  • NAGRC’s Super Goat Breed Poised to Transform Uganda into a Major Exporter

    3216 shares
    Share 1286 Tweet 804
  • Chris Rwakasisi: From Obote’s Security Minister to a Symbol of Forgiveness in Today’s Uganda

    41 shares
    Share 16 Tweet 10
  • Col. Samson Mande: Why I fled Uganda and how I reconciled with Museveni

    36 shares
    Share 14 Tweet 9
  • 10 dangerous hotspots known for prostitutes in Kampala

    1304 shares
    Share 522 Tweet 326
  • Uganda’s Billionaires 2025: Once Again Sudhir Ruparelia Leads a Resilient Pack

    128 shares
    Share 51 Tweet 32
Facebook Twitter

Contact Information

Watchdog Uganda is a portal for solution journalism, trending news plus cutting edge commentaries in the fields of politics, security, business, tourism, entertainment, technology, agriculture, climate change, environment, public health et al. We also give preference to Ugandan community news and topical discussions. The portal also publishes community news and topical discussions.

Email: editorial@watchdoguganda.com
To Advertise:Click here

Latest News

Forget Bobi Wine’s Kiwani Politics; Uganda’s New Political Darling is Born in Luzzi’s Unfiltered Truth

29th October 2025 at 23:50

Busega-Mpigi Expressway project loan approved

29th October 2025 at 22:51

Check out

  • Trending
  • Comments
  • Latest

NAGRC’s Super Goat Breed Poised to Transform Uganda into a Major Exporter

17th September 2025 at 08:52
Minister Muruli Mukasa

LIST: New salary structure for civil servants starting July 2020 out; scientists, lecturers get juicy pay rise

24th May 2020 at 10:45
Sudhir Ruparelia is the undisputed king of Kampala

Billionaire Sudhir’s wisdom on how to invest in real estate

0

How a boy’s destiny turned from cotton grower to communications guru

0

Forget Bobi Wine’s Kiwani Politics; Uganda’s New Political Darling is Born in Luzzi’s Unfiltered Truth

29th October 2025 at 23:50

Busega-Mpigi Expressway project loan approved

29th October 2025 at 22:51

© 2025 Watchdog Uganda

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • News
    • National
    • Politics
    • World News
    • Media Outreach Newswire
    • Africa News
    • Tourism
    • Community News
    • Luganda
    • Sports
      • Football
      • Motorsport
  • Op-Ed
    • #Out2Lunch
    • Conversations with
    • Politics
    • Relationships
  • Business
    • Agriculture
    • CEOs & Entrepreneurs,
    • Companies
    • Finance
    • Products
    • RealEstate
    • Technology
  • Entertainment
    • Lifestyle
  • People
    • Showbiz
      • Salon Mag
  • Special Report
    • Education
    • Voices
  • Reviews
    • Products
    • Events
    • Hotels
    • Restaurants
    • Places
  • WD-TV
  • Donate
  • China News

© 2025 Watchdog Uganda